SRTS Project Information:
February 24th Update
The project has been awarded to C&D Hughes of Charlotte by MDOT. A preconstruction meeting was held last week (Feb 15) to finalize construction details with the contractor.
Tree removals will be completed from March 1 – through March 31st.
Sidewalk construction will start after Memorial Day tentatively. The contractor anticipates starting on High Street and working their way around the City from there but this is not finalized. We will provide details on locations and dates once we have them.
Rowe PSC will have inspectors on site for the duration of the project.
An overview of the sidewalk installation locations can be found here: Overview – SRTS and detailed pages here: Plan Views – SRTS
Hall/Washington/McClure Project Information:
March 27th Update
The project has been awarded to C&D Hughes of Charlotte by MDOT. A preconstruction meeting was held to finalize construction details with the contractor. Rowe PSC will have inspectors on site for the duration of the project.
Tree removals will be completed the week of March 27th, which may result in temporary access limitations during work days. Construction is tentatively scheduled to start in mid-May.
Island Highway Project Information:
March 27th Update
The project is being managed by Eaton County Drain Commissioner’s Office. Project planning is underway and construction is planned to begin this spring. Check back for more details!