East Lovett Street Project Update For September 8, 2017

Sep 8, 2017

One thing we have learned recently is that Lovett Street is not paved with good intentions. An unforeseen circumstance has frustrated our efforts to have the project completed and the street reopened by Frontier Days.

An issue with the curb was discovered that led to a decision to replace much of the newly installed curb and gutter. (The expense of the additional work will not be charged to the City.) Saw cutting was completed today. Removal and replacement of the curb and gutter will occur on Monday and Tuesday. Grading and paving will take place on Wednesday and Thursday.

In the meantime, we have tried to make the street look as presentable as possible for the weekend.