East Lovett Street Project Update For July 28, 2017

Jul 28, 2017

The primary task for the contractor this week was the installation of new water main. This work is scheduled to be finished today.

This work on the water main was originally planned for next week with sanitary sewer to be completed this week. It was decided, however, to reverse the order of those tasks. Sanitary sewer work is scheduled to begin next week.

Because of the excellent summer weather we are enjoying, this project remains on track for a late-August completion.