Reconstruction of the 100 block of East Lovett Street in downtown Charlotte began on Monday, July 17. The first week’s work involved pavement, curb and sidewalk removal.
The photos above show some of the old coal chutes leading to building basements that were discovered under the sidewalks. The contractor will be providing an estimate for blocking these holes and filling them to remove these voids before new sidewalks are poured.
The following is the tentative schedule of activities associated with the project. The order of various tasks is subject to change and delays can occur due to inclement weather and other unforeseen circumstances.
MEETING DATES | AGENDA LINKS | MINUTES LINKS |
---|---|---|
January 16, 2018 | Agenda | Minutes |
February 20, 2018 | Agenda | Minutes |
March 20, 2018 | Minutes | |
April 17, 2018 | Agenda | Minutes |
May 15, 2018 | Canceled | Canceled |
June 19, 2018 | Canceled | Canceled |
July 17, 2018 | Agenda | Minutes |
August 21, 2018 | Agenda | Minutes |
September 18, 2018 | Agenda | Minutes |
October 16, 2018 | Agenda | No quorum, Meeting Notes: Minutes |
November 20, 2018 | Canceled | Canceled |
December 18, 2018 | Agenda | Minutes |