East Lovett Street Project Update for August 11, 2017

Aug 11, 2017

New water main has been installed and tested. Connections between the new main and abutting properties have also been completed.

Work has now started on the installation of a new sanitary sewer line. In the photo above, a hole is clearly visible in the top of the old sewer. This hole might have been affecting the rate of sewer flow in this area in the recent past.

Construction activities related to the sanitary sewer will continue through next week.