Category Archives: Streets

East Lovett Street Project Update For August 18, 2017

The installation of new sanitary sewer infrastructure was planned for completion today. Work on the installation of new storm sewer is scheduled to begin on Saturday. A delay was experienced due to the need to identify an unknown utility line. It was … Continue reading

Posted in Streets | Comments Off on East Lovett Street Project Update For August 18, 2017

East Lovett Street Project Update for August 11, 2017

New water main has been installed and tested. Connections between the new main and abutting properties have also been completed. Work has now started on the installation of a new sanitary sewer line. In the photo above, a hole is … Continue reading

Posted in Streets | Comments Off on East Lovett Street Project Update for August 11, 2017

Street Closure

Posted in Streets | Comments Off on Street Closure

East Lovett Street Project Update For July 28, 2017

The primary task for the contractor this week was the installation of new water main. This work is scheduled to be finished today. This work on the water main was originally planned for next week with sanitary sewer to be completed … Continue reading

Posted in Streets | Comments Off on East Lovett Street Project Update For July 28, 2017

East Lovett Street Project Update For July 21, 2017

Reconstruction of the 100 block of East Lovett Street in downtown Charlotte began on Monday, July 17. The first week’s work involved pavement, curb and sidewalk removal. The photos above show some of the old coal chutes leading to building … Continue reading

Posted in Streets | Comments Off on East Lovett Street Project Update For July 21, 2017