Agenda Packet For Monday, October 9, 2017 City Council Meeting

Posted in Agenda, City Council | Comments Off on Agenda Packet For Monday, October 9, 2017 City Council Meeting

Lovett Street Project Update For September 15, 2017

Defective curb and gutter were replaced this week and the base course of asphalt was installed. The wearing course of asphalt is due to be installed on Monday with final details of the project completed over the following couple of days. … Continue reading

Posted in Streets | Comments Off on Lovett Street Project Update For September 15, 2017

East Lovett Street Project Update For September 8, 2017

One thing we have learned recently is that Lovett Street is not paved with good intentions. An unforeseen circumstance has frustrated our efforts to have the project completed and the street reopened by Frontier Days. An issue with the curb … Continue reading

Posted in Streets | Comments Off on East Lovett Street Project Update For September 8, 2017

East Lovett Street Project Update For August 25, 2017

Work on underground utilities and infrastructure has been completed. Crews are expected to begin the installation of new curbs and gutters on Saturday. Paving should begin next week. In short, and much to the relief of property owners in this … Continue reading

Posted in Streets | Comments Off on East Lovett Street Project Update For August 25, 2017

East Lovett Street Project Update For August 18, 2017

The installation of new sanitary sewer infrastructure was planned for completion today. Work on the installation of new storm sewer is scheduled to begin on Saturday. A delay was experienced due to the need to identify an unknown utility line. It was … Continue reading

Posted in Streets | Comments Off on East Lovett Street Project Update For August 18, 2017