2016 Street Improvement Program Update #3

May 12, 2016

Consumers Energy is continuing its work replacing gas lines on North Sheldon street in advance of reconstruction work slated to begin at the end of the month.

A pre-construction meeting was held today with the contractor Michigan Paving and Materials. Work will begin slightly later than previously reported with milling of the current surface to start on Beach Street on June 1. Crews will proceed to mill the other streets and then return to each street to adjust manholes, patch and install the asphalt overlay. All work is expected to be completed in two weeks although this schedule could be delayed by rain.